The Evolution of the Fourth Dynasty Pyramids · Chapter 6

Considering the Construction Process of the Pyramid

From an Engineer’s Perspective

Hiroyuki Nagase · 2026 · Book pages 93–102
From The Evolution of the Fourth Dynasty Pyramids: From an Engineer’s Perspective
ISBN 978-4911207901

Next: Chapter 7 — The Three Large Pyramids of King Sneferu

Previous: Chapter 5 — Rethinking the Construction Slopes of the True Pyramid

Continue reading

The PDF reproduces book pages 93–102, including the workforce diagram and the proposed construction-phase model.

Read Chapter 6 (PDF, 10 pages)

Topics covered

The result is a reconstruction of pyramid building as an operation whose workforce, bottlenecks, and daily activities changed with height, construction phase, and season. Its central question is not only how the monument could be built, but how a complex project could continue to function as its requirements changed.

A second pattern follows the annual flood cycle of the Nile. Seasonal agricultural labor could be concentrated on quarrying, stone transport, masonry, and ramp construction during inundation. In the low-water season, different tasks became practical: maintaining and excavating the harbor, obtaining Nile mud for sun-dried bricks, preparing materials, and repairing infrastructure. Surveying, specialist craftsmanship, design, and administration may have continued throughout the year. The chapter connects these seasonal tasks to the mudbrick requirements discussed earlier and to the broader logistical and administrative organization reflected in the Diary of Merer.

This sequence also challenges the idea of a fixed army of laborers working at Giza for decades. The chapter argues that the number and type of workers would have changed as the project advanced. It considers the problems of assigning specialists, releasing or redeploying labor, and managing the transition between stages with very different staffing needs. These are engineering-management inferences, not a surviving ancient staffing record.

From this geometric constraint, the chapter proposes a nonlinear pattern of workforce requirements, organized into four phases: preparation; construction of the core, ramps, and casing; a period of apparent stagnation near the top; and final finishing. During the last phase, workers would descend along the exterior, cutting and polishing the casing stones while dismantling scaffolding and ramps. The available surface area would expand again, so the labor force could grow dramatically before falling away when the work was complete. Figure 6-1 illustrates this proposed change in workforce over the life of the project.

One constraint is imposed by the pyramid’s shape. As the structure rises, each successive course has a smaller area and requires fewer stones. Using a simplified model of Khufu’s pyramid with 203 courses and approximately 2.3 million blocks, Nagase estimates how sharply the number of stones per course decreases. Yet the available working area also shrinks. Near the summit, adding more workers cannot necessarily accelerate the project: there is simply nowhere for them to work. The final core masonry could thus be slow even while the number of blocks remaining became very small.

How would the building of Khufu’s pyramid have been organized over many years? This chapter approaches the project as a manufacturing and construction operation rather than as a single feat of stone lifting. Planning, surveying, quarrying, storing materials, preparing roads, building ramps and scaffolds, placing masonry, and finishing the casing had to be coordinated. Earlier pyramids at Meidum and Dahshur would already have given the builders considerable practical experience.

About this chapter